RFIs & Clarifications

How to Write a Construction RFI That Actually Protects Your Margin — With Examples

By TenderScope·9 min read· UK & USRFIsTender Strategy

A Request for Information (RFI) is one of the most powerful tools a contractor has at tender or bid stage — and one of the most underused. A well-written RFI doesn't just get you a clarification. It creates a commercial paper trail, documents your pricing assumptions, and protects you from scope disputes after award. Here's how to write them properly.

🇬🇧 UK — Tender RFIs & Clarifications 🇺🇸 US — Bid RFIs & Addenda Requests
73%
Of construction disputes involve scope or information gaps that existed at bid stage
RFI deadline
Typically 7–14 days before tender return — after this, you price blind
Paper trail
A submitted RFI is evidence. A mental note is not.

What Is a Construction RFI?

An RFI — Request for Information — is a formal written question submitted to the client or their design team during the tender or bid period. It asks for clarification on information that is missing, ambiguous, or contradictory in the tender pack or bid documents.

In the UK, RFIs are sometimes called clarification questions, tender queries, or pre-tender enquiries. In the US, they're universally called RFIs during bidding. Under NEC contracts, the equivalent mechanism post-award is an early warning notice. The terminology varies — the purpose doesn't.

💡 Why RFIs Matter Commercially

An RFI submitted before the tender return date creates a formal record that you identified a gap or ambiguity before pricing. If the issue becomes a dispute after award, your RFI is evidence. If you didn't raise it, you may be deemed to have accepted the risk.

The Four Elements of an Effective RFI

Most RFIs are too vague to be useful. "Please confirm the extent of electrical works" tells the client nothing specific and gives you no protection. A proper RFI has four elements — reference, question, assumption, and commercial impact.

✗ Weak RFI — Avoid This
Subject
Electrical scope query
Question
Please can you confirm the full extent of the electrical works included in this package?
Why This Fails
No document reference. No specific gap identified. No pricing assumption stated. The client can't answer it meaningfully and it gives you no commercial protection.
✓ Strong RFI — Use This Format
RFI Reference
RFI-003
Subject
Ward 7B distribution board drawing E-BD-004 — not issued
Document Reference
Drawing schedule, electrical-tender-pack.pdf, page 11 — drawing E-BD-004 listed as "Not Issued"
Question
Drawing E-BD-004 showing the Ward 7B distribution board arrangement is listed in the drawing schedule but has not been issued with the tender pack. When will this drawing be available for pricing?
Pricing Assumption
Ward 7B distribution board excluded from pricing pending issue of drawing E-BD-004. A provisional sum of £15,000 has been included for this element.
Commercial Impact
Without this drawing, the Ward 7B electrical distribution cannot be designed or priced accurately. Scope and cost risk is significant.

When to Submit RFIs

Most tender packs and bid packages include an RFI or clarification deadline — typically 7–14 days before the return date. This gives the client time to issue an addendum with answers before you submit your price. Missing this deadline means you price blind on every unanswered question.

In practice, you should identify all your RFIs during your initial document review — ideally within the first day of receiving the pack — and batch-submit them as early as possible. Late RFIs get late answers. Some never get answered at all.

⚠ US Bidders — Check Addenda Obligations

In US construction, the client responds to RFIs by issuing an addendum to all bidders. You are typically required to acknowledge receipt of all addenda in your bid submission. Failure to acknowledge an addendum can result in bid rejection — check the Instructions to Bidders carefully.

The 10 Most Common RFI Topics at Tender Stage

Based on analysis of hundreds of tender packs, these are the most frequent issues that should trigger an RFI:

IssuePriorityUK TermUS Term
Missing quantity scheduleCRITICALBill of Quantities not providedNo schedule of values / quantity takeoff
Missing or not-issued drawingCRITICALDrawing listed "Not Issued"Drawing listed but not in bid set
Hazardous materials survey not providedCRITICALAsbestos survey not issuedHazmat / environmental survey missing
Contradicting specificationsHIGHSpec conflicts with drawingSpec section conflicts with drawing
Undefined provisional sumHIGHProvisional sum stated but not scopedAllowance stated but not defined
Temporary works responsibilityMEDTemporary works not allocatedShoring / falsework responsibility unclear
Scope of commissioningMEDCommissioning and witnesses not definedCommissioning scope and witnessing not defined
Interface trade responsibilitiesMEDBuilder's work by others?Supporting trades by GC or sub?
Working hours restrictionsMEDPermitted noisy working hoursNoise ordinance / permitted work hours
Temporary power and lightingMEDTemporary supply — by whom?Temp power — GC or sub responsibility?

RFI Examples — Real Scenarios

Example 1 — Missing Bill of Quantities (UK)

✓ RFI-001
Subject
Bill of Quantities provision for electrical package
Reference
Tender submission requirements, Section 3 — "Fully priced Bill of Quantities" listed as a required submission document
Question
A fully priced Bill of Quantities is listed as a required submission document, however no BoQ has been provided in the tender pack. Can the Employer provide a BoQ or detailed measurement schedule for the electrical works?
Pricing Assumption
Quantities measured from drawings and specifications provided. Pricing includes detailed assumptions on quantities, which are stated in the submission.
Commercial Impact
Significant pricing risk on quantities without a detailed BoQ. Contractor accepts no liability for quantity errors where information was not provided.

Example 2 — Missing Hazmat Survey (US)

✓ RFI-002
Subject
Environmental / hazardous materials survey — not issued
Reference
Project specification Section 02 82 00 — references environmental assessment report EAR-2024-0112 which has not been included in the bid package
Question
The specification references an environmental assessment report identifying ACM (asbestos-containing materials) in the existing structure, but this report has not been included in the bid documents. Can this report be issued prior to the bid return date?
Pricing Assumption
All asbestos abatement, hazmat removal, and associated delay costs excluded from bid. A $25,000 allowance has been included for potential schedule impacts pending report review.
Commercial Impact
Without the hazmat survey, ACM extent and abatement requirements are unknown. Schedule and cost risk is significant and cannot be quantified.

Example 3 — Contradicting Specifications

✓ RFI-004
Subject
Fire alarm specification — reference to superseded standard
Reference
Specification Section M40, Clause 3.2.1 — fire stopping specification references BS 476 Part 22 which was withdrawn in 2017
Question
Section M40 Clause 3.2.1 references fire stopping tested to BS 476 Part 22, which has been superseded by BS EN 1366. Can you confirm whether compliance with BS EN 1366 is acceptable, or whether a specific BS 476 tested product is required?
Pricing Assumption
Fire stopping products priced to BS EN 1366 compliance. If BS 476 tested products are specifically required, pricing adjustment may be required.
Commercial Impact
BS 476 tested products are significantly more limited in availability and may carry a cost premium. Clarification required before final pricing.

"Every RFI you submit is a line of defence. Every ambiguity you don't raise is a risk you've accepted — whether you meant to or not."

What to Do When You Don't Get an Answer

Sometimes the RFI deadline passes and your question isn't answered. Or the addendum comes back with "noted" or "contractor to allow" — which tells you nothing. In these situations, your pricing assumption becomes your protection.

Every RFI you submit should include a clear statement of what you're pricing on if no answer is received. That assumption, stated in your submission qualifications, is your commercial defence. If the scope turns out to be different from your assumption and you have a written record of having asked, you have the basis for a variation claim.

✓ Best Practice

Include your pricing assumptions in two places: in the RFI itself (submitted before the deadline), and in your tender submission qualifications. This double-documentation makes it clear to any future dispute resolution body that the issue was raised, not overlooked.

NEC Early Warning Notices — The UK Equivalent Post-Award

Under NEC4 contracts, RFIs at tender stage become Early Warning Notices (EWNs) after contract award. An EWN is a formal notification that an issue exists which may affect cost, time, or quality. The obligation is mutual — both contractor and project manager must give early warning of emerging risks.

Failing to give an EWN when you were aware of a risk can reduce or eliminate your entitlement to additional time or money. Good tender-stage RFI discipline translates directly into good post-award contract management.

Building Your RFI Log

Keep a simple log of every RFI you submit, the date submitted, the response received, and what you priced on. This log is your evidence pack if any of these issues become disputes after award.

📋 RFI Submission Checklist
Reference number — sequential, easy to cross-reference in your submission
Specific document reference — page number, clause, drawing number. Not "the spec says..."
Single, clear question — one RFI per issue. Don't bundle multiple questions
Pricing assumption stated — what you're including or excluding pending the answer
Commercial impact stated — why this matters to your price
Submitted before the RFI deadline — after the deadline, late queries may be ignored
Logged and tracked — date submitted, response received, used in pricing
Repeated in qualifications — assumptions re-stated in your tender submission

Get your RFIs written for you

TenderScope analyses your full tender pack or bid package and generates a complete set of ready-to-send RFIs — referenced to the documents, with pricing assumptions included. First report free.

Get Your Free RFI Analysis →